Portion of Flagler Drive closed for Stormwater work

When:  Beginning Tuesday, June 30, 2009, at 6:00 a.m.
Affected Area:  Flagler Drive between Banyan Blvd. and Fern Street

Due to necessary stormwater improvements, Flagler Drive will be closed between Banyan Boulevard and Fern Street beginning Tuesday, June 30, 2009, at 6:00 a.m.  The road is expected to reopen by September 30, 2009.

All residents, business and their customers will have access to their destinations near the construction area.  The City has coordinated with local businesses and residences in an effort to minimize the project’s impact.  The new City public docks along Flagler Drive will remain open to the public throughout the road work.  The project will not affect the City’s 4th on Flagler festivities which will be located between Fern Street and Lakeview Avenue.

Northbound traffic on Flagler Drive will detour at Fern Street to Olive Avenue.  Southbound traffic on Flagler Drive will detour at Banyan Boulevard to Narcissus Avenue.